80618 (2024). Hon Phil Twyford to the Minister of Health

Written Question
Published date: 24 Dec 2024
80618 (2024). Hon Phil Twyford to the Minister of Health: What is the current status of the birthing suites at Waitakere Hospital as of November 2024?
Hon Dr Shane Reti:  I am advised that the anticipated date of practical completion for this project is December 2026. Please note, forecasted completion dates may be subject to change based on various factors, including system/cost pressures, necessary approvals, etc. There are key stage gates where accuracy of an estimate is enhanced, these are generally at business case decision, at the end of each design phase and main contract award.