75576 (2024). Hon Dr Duncan Webb to the Minister of Housing
Written Question
Published date: 04 Dec 2024
75576 (2024). Hon Dr Duncan Webb to the Minister of Housing: How much money was projected to be spent on the Heath Street, Christchurch Kāinga Ora development as at 13 October 2023, and how much money (if any) has already been spent on this project as at 18 November 2024?
Hon Chris Bishop: I am advised by Kāinga Ora – Homes and Communities that the Heath Street project was delivered in February 2024, as outlined in WPQ 71135 (2024), and the project budget was $1,710,152.