Hon Simeon Brown: As the Member will be aware, the Ōtaki to North of Levin Road of National Significance is expected to begin construction next year. I am advised that NZTA's spend on the Ōtaki to North of Levin project is broken down as follows:
- Pre-implementation: $5,314,130
- Property: $31,172,051
- Implementation: $28,686,944