66382 (2024). Tangi Utikere to the Minister of Transport
Written Question
Published date: 03 Nov 2024
66382 (2024). Tangi Utikere to the Minister of Transport: How much has been spent since November 2023 on the Hawke's Bay Expressway project, if any?
Hon Simeon Brown: As the Member will be aware, the Hawke’s Bay Expressway has been identified as one of the first seven Roads of National Significance that are expected to begin procurement, enabling works and construction in the next three years. I am advised that NZTA has spent $2,150,839 since November 2023.