62465 (2024). Lan Pham to the Minister for the Environment
Written Question
Published date: 10 Oct 2024
62465 (2024). Lan Pham to the Minister for the Environment: What was the average time a resource consent took to be granted from the application date under the COVID-19 Recovery (Fast-track Consenting) Act 2020?
Hon Penny Simmonds: The average number of working days from lodgement to decision for listed projects is 88 days.
The average number of working days from lodgement to decision for referred projects is 114 days.
The averages exclude any days an application was on suspension.