55450 (2025). Hon Kieran McAnulty to the Minister of Health
Written Question
Published date: 09 Dec 2025
55450 (2025). Hon Kieran McAnulty to the Minister of Health: What is the current estimated total cost of Linear Accelerators Replacement, Auckland City Hospital, and how does that compare with the original approved budget, as at 24 November 2025?
Hon Simeon Brown: I am advised that, as part of our focus on putting patients first and ensuring all New Zealanders have access to timely, quality healthcare, the forecast cost for Linear Accelerators (MV1 and MV6) Replacement, Auckland City Hospital, is currently on budget. I am further advised that the total approved budget for the project is $17,294,460 (Capex) and $6,686,890 (Opex).