55236 (2025). Hon Kieran McAnulty to the Minister of Transport

Written Question
Published date: 09 Dec 2025
55236 (2025). Hon Kieran McAnulty to the Minister of Transport: What is the forecast completion date for Waihoehoe Rd Upgrade, and how has that changed since its inclusion in the Government’s 20 July 2025 Beehive press release titled “Infrastructure projects to drive jobs and growth”, as at 24 November 2025?
Hon Chris Bishop: The piling work is scheduled to conclude in May 2026 with the main contract to follow. Completion is expected to be in mid-2028.