55223 (2025). Hon Kieran McAnulty to the Minister of Transport

Written Question
Published date: 09 Dec 2025
55223 (2025). Hon Kieran McAnulty to the Minister of Transport: What percentage of physical construction work has been completed on SH29 Tauriko Bridge, as at 24 November 2025?
Hon Chris Bishop: I am advised that as at 24 November approximately 1.1% of construction work has been completed.