55216 (2025). Hon Kieran McAnulty to the Minister of Transport
Written Question
Published date: 09 Dec 2025
55216 (2025). Hon Kieran McAnulty to the Minister of Transport: What percentage of physical construction work has been completed on SH1 Otaki–Levin, as at 24 November 2025?
Hon Chris Bishop: I am advised that construction to date has mainly been enabling works. Approximately 3% of the project has been completed.