50238 (2025). Hon Kieran McAnulty to the Minister of Transport
Written Question
Published date: 04 Nov 2025
50238 (2025). Hon Kieran McAnulty to the Minister of Transport: What is the total amount spent to date on the construction of SH1 Ōtaki to north of Levin, Horowhenua, as at 17 October 2025?
Hon Chris Bishop: I am advised that as at 30 September 2025, which is the latest figure available, $452.5 million has been spent on this project. Of that $164 million has been spent during the construction phase.