50200 (2025). Hon Kieran McAnulty to the Minister of Education: What percentage of physical construction work has been completed on School property projects referenced in the Government’s 20 July 2025 Beehive press release titled “Infrastructure projects to drive jobs and growth”, as at 17 October 2025?
Hon Erica Stanford: Since July 2025, 102 Ministry of Education led projects worth $307 million have started construction. Of these, four projects worth $0.9 million have been completed.