48969 (2025). Scott Willis to the Minister of Transport

Written Question
Published date: 21 Oct 2025
48969 (2025). Scott Willis to the Minister of Transport: How many publicly available EV chargers, if any, are being built in New Zealand per month on average to acheieve the government's goal of 10,000 EV chargers by 2030?
Hon Chris Bishop: There has been an average of around 16 charge points installed per month since 1 January 2024. This is based off a total of 346 charge points installed since 1 January 2024.