47345 (2025). Hon Kieran McAnulty to the Minister of Housing

Written Question
Published date: 17 Oct 2025
47345 (2025). Hon Kieran McAnulty to the Minister of Housing: What was the final cost of the Meadowbank complex at Puroto Street as recorded by Kāinga Ora and how does that figure breakdown by engineering, architect, council fees, infrastructure, building construction and other costs?
Hon Chris Bishop: Kāinga Ora – Homes and Communities advises me that the total cash investment was $11,050,096 including GST, and the total construction budget was $8,752,210 including GST. The breakdown of the total cash investment is: • Engineering, architecture and project management: 10% • Council fees: 2% • Construction: 70% • Site works: 15% • Development Contribution and Network charges: 3%