40494 (2025). Tangi Utikere to the Minister for Rail
Written Question
Published date: 02 Sep 2025
40494 (2025). Tangi Utikere to the Minister for Rail: What is the final confirmed cost of cancelling the iReX ferry contract, broken down by payments to the shipyard, landside infrastructure design and consenting fees, professional services and consultancy costs incurred since December 2023, and any other categories of expenditure?
Rt Hon Winston Peters: As announced by KiwiRail on 15 August 2025, $671 million was spent in total on Project iReX of which $449 million was for landside infrastructure and management while $222 million was paid to Hyundai. Of the $222 million, $144 represented the final settlement payment. KiwiRail is unable to detail the Hyundai payments as Hyundai is still negotiating with its suppliers to resolve their claims. To the extent that any further details can be provided, you will need to place an OIA request with KiwiRail as the responsible party for Project iReX and the holder of that information.