39668 (2026). Tangi Utikere to the Minister for Rail

Written Question
Published date: 21 Sep 2026
39668 (2026). Tangi Utikere to the Minister for Rail: How much of the $1.9 billion total programme cost for the ferry replacement programme is not counted within the $1.704 billion taxpayer contribution, and who bears each component of that difference?
Rt Hon Winston Peters: $1.924 billion minus $1.704 billion equals $220 million. $110 million from Port Marlborough. $100 million from CentrePort, and $10 million from the NZTA. Again, you can read about all of this in our speech: https://www.beehive.govt.nz/speech/common-sense-back-helm