39148 (2024). Hon Dr Ayesha Verrall to the Minister of Health
Written Question
Published date: 14 Jul 2024
39148 (2024). Hon Dr Ayesha Verrall to the Minister of Health: What is the anticipated date of completion of the ‘design’ project phase of the ‘Wāhi Oranga - Acute Mental Health Inpatient Unit Upgrade, Nelson Hospital’, as part of Te Whatu Ora’s Infrastructure and Investment projects, as of 1 July 2024?
Hon Dr Shane Reti: I am advised that the design phase of this project was completed in November 2022.