38074 (2025). Hon Kieran McAnulty to the Minister of Housing
Written Question
Published date: 17 Aug 2025
38074 (2025). Hon Kieran McAnulty to the Minister of Housing: What changes, if any, have been made to the forecasted completion timelines for Hobsonville Point, Northcote, Roskill, Oranga, Māngere, Tāmaki, Lakeside, and Te Rā Nui since Kāinga Ora’s 2024-2025 financial reset, broken down by urban development large-scale project?
Hon Chris Bishop: Kāinga Ora – Homes and Communities advises me that no changes to completion timelines have changed in Tamaki, Te Ra Nui and Lakeside Developments.
In Hobsonville Point two development partners have extended construction timelines.
In Northcote and Oranga construction dates have been extended to the financial year 2030.
Decisions made in Budget 2025 to withdraw funding from neighborhoods in the Mangere and Roskill Developments which will see these developments deferred indefinitely.