38032 (2025). Tangi Utikere to the Minister of Transport
Written Question
Published date: 17 Aug 2025
38032 (2025). Tangi Utikere to the Minister of Transport: What environmental impacts have been identified as part of the Ōtaki to north of Levin highway construction, and what is the estimated cost of environmental mitigation measures?
Hon Chris Bishop: I am advised by NZTA that effects that were assessed for mitigation as part of Ō2NL, as is typical with other large highway projects, include:
• Cultural
• Transportation
• Noise and vibration
• Air quality
• Landscape and visual
• Natural character
• Social
• Hydrology, groundwater and surface water
• Contaminated land
• Ecology
• Archaeology and built heritage
• Productive land
• Economic
• Property, network utilities and infrastructure
• Natural hazards
NZTA estimates that the cost of environmental mitigation measures to be $90 million.