35870 (2026). Tangi Utikere to the Minister of Transport

Written Question
Published date: 24 Aug 2026
35870 (2026). Tangi Utikere to the Minister of Transport: What were the seven recommendations of the Gateway 3 review of the Warkworth to Te Hana project conducted between 4 and 8 May 2026, which returned a Green/Amber delivery confidence assessment, which of those recommendations had been implemented in full as at the date of answering, and what is the implementation timeframe for any that remain outstanding?
Hon Chris Bishop: I refer the Member to my response to Written Parliamentary Question 34428 (2026).