34431 (2026). Tangi Utikere to the Minister of Transport
Written Question
Published date: 18 Aug 2026
34431 (2026). Tangi Utikere to the Minister of Transport: Who will independently verify the Northway consortium's performance against the Warkworth to Te Hana Key Performance Indicators, and at whose cost?
Hon Chris Bishop: I am advised that there is no independent verification of the Northway consortium’s performance against Key Performance Indicators. This assessment is done by NZTA.
The Independent Reviewer is jointly engaged and funded by NZTA and Northway SPV. The Independent Reviewer is responsible for verifying that the Works Requirements have been met and that the Works Completion Tests have been achieved.