33575 (2025). Tangi Utikere to the Minister of Transport
Written Question
Published date: 22 Jul 2025
33575 (2025). Tangi Utikere to the Minister of Transport: Further to his reply to Question 29614 (2025), how many complaints from the road cone hotline were received by NZTA and how many of those were forwarded to the relevant maintenance or infrastructure project contractors?
Hon Chris Bishop: I am advised by NZTA that it received 155 queries from WorkSafe between 3 June 2025 and 4 July 2025. 147 have been processed by the NZTA Contact Centre and referred to the relevant maintenance or infrastructure project contractor for further review. Eight queries were identified as not requiring further referral.