33482 (2026). Tangi Utikere to the Minister of Transport

Written Question
Published date: 18 Aug 2026
33482 (2026). Tangi Utikere to the Minister of Transport: Which Roads of National Significance, if any, hold a resource consent or Fast-track approval that has been granted but not yet given effect, and which of those have a lapse date within the next five years?
Hon Chris Bishop: The Roads of National Significance that have designation alterations, resource consents, and other statutory approvals under the Fast-track Approvals Act are Takitimu Northern Link Stage 2 and Belfast to Pegasus Project. The resource consents granted under the FTAA have lapse dates longer than five years.