32007 (2026). Tangi Utikere to the Minister for Rail
Written Question
Published date: 29 Jul 2026
32007 (2026). Tangi Utikere to the Minister for Rail: Further to reply 30345 (2026), what is the current forecast cost at completion for the Cook Strait ferry replacement programme against the budget approved by Cabinet, expressed as a dollar variance, if any?
Rt Hon Winston Peters: $1.704 billion is the current taxpayer budget for our contribution to the programme. This gives a variance of $0.000 billion against the budget approved by Cabinet.
As a mathematical equation: $1.704 billion minus $1.704 billion equals $0.000 billion.