31825 (2026). Tangi Utikere to the Minister of Transport

Written Question
Published date: 29 Jul 2026
31825 (2026). Tangi Utikere to the Minister of Transport: What is the NZ Transport Agency's total expenditure to date on SH1 Cambridge to Piarere, if any, broken down by financial year and by project phase?
Hon Chris Bishop: 2024/25 Investment Case $0.076 million Pre Implementation $13.6 million Property $17 million 2025/26 (as at 31 May 2026) Investment Case $0.2 million Pre Implementation $20 million Implementation “Early Works” $1.3 million Property $85.3 million