31493 (2026). Tangi Utikere to the Minister of Transport

Written Question
Published date: 03 Aug 2026
31493 (2026). Tangi Utikere to the Minister of Transport: For how many Roads of National Significance in the July 2026 Major Transport Projects Pipeline is route protection the only substantive activity funded in the current 2024–27 National Land Transport Programme period?
Hon Chris Bishop: Only one project (the North West Alternate State Highway) has route protection as the only substantive activity funded in the current 2024–27 National Land Transport Programme