31457 (2026). Tangi Utikere to the Minister of Transport: What is the current cost estimate for the SH76 Brougham Street improvements Package 2 (corridor)?
Hon Chris Bishop: SH76 Brougham Street has an estimated project cost of $100–$152 million. A cost estimate for Package 2 is not yet available.