25946 (2026). Tangi Utikere to the Minister of Transport
Written Question
Published date: 23 Jun 2026
25946 (2026). Tangi Utikere to the Minister of Transport: How much, if any, of the $675 million announced as approved on 20 October 2025 for consenting, design, route protection, site investigations and early works had been spent as at 5 June 2026?
Hon Chris Bishop: I am advised by NZ Transport Agency Waka Kotahi, that as at the end of April 2026, $323.8 million of the $675 million approved for pre-implementation work on Roads of National Significance has been spent. Pre-implementation includes the activities referenced in the question, as well as additional activities required to prepare the projects for construction.