23830 (2025). Arena Williams to the Minister for Building and Construction
Written Question
Published date: 30 May 2025
23830 (2025). Arena Williams to the Minister for Building and Construction: Has the Seismic Review Steering Group's "Final report summarising findings and providing recommendations for changes to the Earthquake Prone Building system to manage life-safety risk in existing buildings in a workable, equitable and proportionate way" been finalized, and if so, what is the name and date of the document?
Hon Chris Penk: The Terms of Reference for the review of risk management in existing buildings indicates that a report summarising the findings and providing recommendations for changes to the EPB system will be completed in Q2 2025. I expect to see this report in the near future.