12812 (2025). Camilla Belich to the Minister of Revenue: What is the total amount, if any, spent on temporary accommodation for staff, contractors, or consultants by any agencies under the Minister’s responsibility since 27 November 2023, broken down by agency and purpose?
Hon Simon Watts: Officials advise Inland Revenue spent $0.497 million on temporary accommodation from 1 November 2023 to 31 March 2025.
Of this $0.497 million, $0.056 million was spent due to seismic works, $0.093 million was spent due to lease expiry and $0.348 million due to seismic works and site consolidation.