8991 (2024). Shanan Halbert to the Minister of Education

Written Question
Published date: 12 May 2024
8991 (2024). Shanan Halbert to the Minister of Education: How many, if any, school construction projects in the Northcote electorate have been postponed or downscaled between and inclusive of November 2023 and April 2024, by school name and date?
Hon Erica Stanford: I am advised by the Ministry of Education that a pre-construction project at Target Road school was subject to reduced scope in November 2023, and a pre-construction project at Willow Park school was paused in February 2024. These were operational decisions made by the Ministry. Both of these projects are also subject to the Ministry’s Value for Money review. The Ministry’s review is independent of the Ministerial Inquiry into school property.