6092 (2026). Tangi Utikere to the Minister of Transport
Written Question
Published date: 09 Mar 2026
6092 (2026). Tangi Utikere to the Minister of Transport: Does he agree with Tim Costley that “the geotechnical work has already begun” for the second Mt Victoria Tunnel (and/or the Terrace Tunnel duplication); if so, what evidence supports this, if any, including (a) the contract(s) let, (b) the contract value(s), (c) the notice-to-proceed date(s), and (d) the scope of work?
Hon Chris Bishop: Yes, I do. Geotechnical investigations were completed on 20 February 2026.
The evidence is that there were contractors undertaking this work in the Town Belt between November 2025 and February 2026.
Further information is available on the NZTA website at: https://www.nzta.govt.nz/projects/sh1-wellington-improvements/mt-victoria-tunnel-geotechnical-investigations.