5981 (2026). Scott Willis to the Minister for Energy
Written Question
Published date: 09 Mar 2026
5981 (2026). Scott Willis to the Minister for Energy: What advice or information, if any, did the Minister rely on to arrive at the "north of a billion dollars" figure for an LNG import terminal?
Hon Simon Watts: An estimated cost range for the facility services is between $90m - $180m per year. Final costs are still subject to the current procurement process and so will not be publicly released at this time.