4155 (2026). Dr Tracey McLellan to the Minister of Corrections

Written Question
Published date: 27 Feb 2026
4155 (2026). Dr Tracey McLellan to the Minister of Corrections: What assurances, if any, have been received from the Treasury regarding the fiscal sustainability of the Accelerated Capacity Project and the longer-term High-Security Capacity Programme?
Hon Mark Mitchell: I am advised that both the Accelerated Capacity Project and the High Security Capacity Programme progressed through the Treasury’s Better Business Case process and were reported through the Treasury’s Quarterly Investment Reporting.