3834 (2024). Hon Dr Ayesha Verrall to the Minister of Health
Written Question
Published date: 10 Apr 2024
3834 (2024). Hon Dr Ayesha Verrall to the Minister of Health: What is the anticipated date of completion of the ‘deliver’ project phase of the ‘Rural Primary Birthing Unit Construction, Wanaka and Clyde’, as part of Te Whatu Ora’s Infrastructure and Investment projects?
Hon Dr Shane Reti: I am advised that the anticipated practical completion date for the Wanaka unit is July 2024, and anticipated practical completion date for the Clyde unit is October 2025.