3303 (2024). Hon Dr Ayesha Verrall to the Minister of Health

Written Question
Published date: 03 Apr 2024
3303 (2024). Hon Dr Ayesha Verrall to the Minister of Health: What is the anticipated date of completion of the ‘deliver’ project phase of ‘Building For The Future - Fit-out of shelled theatres, inpatient wards and procedure rooms, Tōtara Haumaru, North Shore Hospital.’, as part of Te Whatu Ora’s Infrastructure and Investment projects?
Hon Dr Shane Reti: I am advised that the anticipated date for practical completion (deliver phase) of this project is April 2024.