3285 (2024). Hon Dr Ayesha Verrall to the Minister of Health

Written Question
Published date: 03 Apr 2024
3285 (2024). Hon Dr Ayesha Verrall to the Minister of Health: What is the anticipated date of completion of the ‘deliver’ project phase of the ‘Manukau Superclinic expansion and planned care capacity increase, Manukau Health Park’, as part of Te Whatu Ora’s Infrastructure and Investment projects?
Hon Dr Shane Reti: I am advised that the anticipated date for practical completion (deliver phase) of this project is November 2025.