854 (2024). Hon Dr Megan Woods to the Minister of Transport
Written Question
Published date: 04 Mar 2024
854 (2024). Hon Dr Megan Woods to the Minister of Transport: What progress, if any, has been made on the detailed design and consenting for each of the components of the SH76 Brougham Street upgrade project?
Hon Simeon Brown: I am advised that NZTA is reviewing designs which will be complete by the end of March 2024, and is progressing work on consenting and property purchases.