385 (2026). Hon Willow-Jean Prime to the Minister of Education
Written Question
Published date: 12 Feb 2026
385 (2026). Hon Willow-Jean Prime to the Minister of Education: When does she expect the Albany Junior High School project she announced on 10 September 2025 to be completed and when was work scheduled to begin?
Hon Erica Stanford: The construction of decant block will commence in early 2026, which when complete will allow for the redevelopment works to proceed. These are scheduled for completion for the start of 2028.